Hopefully dredging will begin around January 15, 2008 and end on March 31, 2008.

From the U.S. Army Corps of Engineers web site.

Jones Inlet, NY
Federal Navigation Channel Maintenance of
Infrastructure and Stewardship

FACT SHEET DECEMBER 2007/JANUARY 2008

DESCRIPTION: The periodic maintenance dredging of Jones Inlet federal navigation channel and deposition
basins with placement on the beach at Point Lookout, Hempstead, New York, contingent on available
federal/non-federal funding in FY2008.

AUTHORIZATION: The federal navigation project for Jones Inlet, NY was authorized by the Rivers and
Harbors Act of 1945, 77th Congress, 1st Session, Document No. 409.

COMMERCE: The 2006 commercial tonnage for Jones Inlet was approximately 10,000 tons. The five-year
average annual commercial tonnage at Jones Inlet is less than 2,500 tons, consisting mainly of fish and fish
products, boat related supplies, metal scraps and fuel oil.

FUNDING: The State of New York has provided $7.6M for the dredging and beach placement of the sand,
including environmental coordination, Plans and Specs, and developing the Contributed Funds Memorandum of
Agreement for the project. This CFMOA was fully executed on Nov 8, 2007. $100K federal funding is in the
President's budget request for FY08. In FY07, $68K was provided in the FY2007 Workplan. The funds were
used to update the project Plans and Specifications, conduct a deep water survey at the inlet, and coordinate
with the Town of Hempstead, the NYSDEC, and the US Coast Guard.

STATUS: Federal project funds are provided in FY08 for updated environmental coordination and a survey.
$7.6M funds from the State of NY have been received by the Corps and are expected to be accessible by
December 10, 2007. A deep water survey was performed in mid-January 2007, and a Specifications Survey in
October 2007, which were coordinated with the US Coast Guard for (re-)positioning of the buoys to mark
available deep water for transiting the inlet. There are more than 700,000 cubic yards of shoals in the federal
channel and deposition basin. A bid opening is scheduled for December 12, 2007 with subsequent December
award and Notice to Proceed. Project is expected to be dredged between Jan 15-Mar 31, 2008.
The project was last maintained in 1995/96 with the removal of approximately 459,000 CY of sand which was
beneficially reused as beach nourishment. The material was placed along the severely eroded areas of the Point
Lookout Beach.

CONTACT: Joseph Olha, Project Manager, (917) 790-8404
mailto:joseph.olharb2@gr5tusace.army.mil
U.S. Army Corps of Engineers, New York District
26 Federal Plaza
New York, NY 10278
http://www.nan.usace.army.mil
District Area: NY #3
 
FINALLY ...... Think we can toss em some money to dredge my slip since they will be here anyway ???

Rob
 
Glad to hear it will be getting done! Fire Island is probably going to be due soon also.
 
Fire Island is being done now. Capt. Paul was giving updates over on noreast.
 
Louis, good to hear it. There was a stretch that was getting a little shallow this past season.
 
I noticed that some floating pipes and barges are starting to be staged in Reynolds Channel. Maybe this will finally happen!
 
Wow i think im being IGNORED!!!!

Sorry couldnt help myself... kidding .. smily faces... JOKE ???
 
Dredging started on 1/15 and has been going 24/7. So far the dredge has been dredging between the JI buoy and the first set of buoys. Sand has been pumped onto Point Lookout's Civic and Middle beaches so far. The project was estimated to take approximately six weeks.
 
Rob,
I thought about telling you that I did not know but decided to ignore you instead. However, I am disappointed that you got the answer in less than 2 hours. ;)

Thanks for posting Adam. Should be good to go in the spring.
 
I finally got a chance to post some photos of the dredging.
P1010006.jpg

P1010007.jpg

P1010012.jpg

P1010020.jpg

P1010035.jpg

P1010024.jpg
 
Jones inlet and fire island inlets have been dredged!

Bring on the warm weather.......

Rob
 
I will be using the Fire Island Inlet, for the first time, at the end of March will it be marked and open?
 