"Doubling up" I found locally meant running a second line to the same points, each tied off separately.
For hurricane prep this may help a little, but the better "definition" to use in this context would be: Running a second set of lines to different points that will perform the same function.
To truely have a second line of defense, you need to eliminate any common point of failure.
For severe weather, doubling up means adding additional lines to points I'd normally not use. I have a std setup with 8 lines running to poles and to the dock.
(I'm stern in with a fixed dock with 4 piles defining the slip).
Example.. For the spring lines..Fore & aft lines share a midships cleat. During weather, I run an additional line for each that performs the same function.
To backup the primary forward spring lines, I run an set forward from my stern cleat to the midships piling (or to the bow piling if I don't have on mid-ship). An additional set runs from the bow to the stern piling/dock cleat.
This way, if one line/pile/cleat fails, there is another line that will serve the same function.
I had a boat next to me, double up his bow lines using the same attachment points and the stbd cleat let loose. He rubbed on the pile between us the entire storm..
Had he belayed the second line to the port cleat and vice versa, the failure of the stbd cleat wouldn't have mattered as the second line attached to the oposite cleat would have taken the load..