Engine components on the 2-month-old amphibious transport dock ship USS New York failed during a recent at-sea assessment, forcing the U.S. Navy to keep the ship pierside at Naval Station Norfolk for repairs.
The Navy described the failed equipment as main bearings on the ship's main propulsion diesel engines, a component that holds in place the ship's engines and propulsion gear. The Northrop Grumman-built New York has four main Colt-Pielstick diesel engines; it's unclear how many are affected.
Navy engineers found the problems during a weeklong, post-delivery underway examination of the ship's engines, said Lt. Cmdr. Herbert Josey, a spokesman for Naval Surface Force Atlantic in Norfolk. After the damage was found, the ship returned to Naval Station Norfolk under its own power.
The failed components are under warranty and will be repaired by Northrop and the engine manufacturer, Josey said.
Engineers are now working to determine whether the problems on the New York could also affect other ships in the San Antonio class, which are built at Northrop's Gulf Coast shipyards.
The Navy is also working with the manufacturers to determine the cause of the engine problems, including an examination of maintenance practices, engine manufacturer quality control, shipbuilder practices and training, Josey said.
Northrop spokeswoman Margaret Mitchell-Jones said Friday in a statement that the company "is supporting the Navy in their analysis of the situation, however we defer any additional comment on commissioned ships to the Navy."
Homeported at Naval Station Norfolk, the ship was built in part with 7.5 tons of steel salvaged from the World Trade Center. The ship's Nov. 7 commissioning in New York City was the subject of much celebration and media attention.
Sun Jan 10, 2010 9:57 pm
This doesn't sound very good to me. The care and feeding of such important components during the long building process--several years---is the responsibility of the builder. Here's another opportunity for the taxpayor to pay through the nose.
The Navy described the failed equipment as main bearings on the ship's main propulsion diesel engines, a component that holds in place the ship's engines and propulsion gear. The Northrop Grumman-built New York has four main Colt-Pielstick diesel engines; it's unclear how many are affected.
Navy engineers found the problems during a weeklong, post-delivery underway examination of the ship's engines, said Lt. Cmdr. Herbert Josey, a spokesman for Naval Surface Force Atlantic in Norfolk. After the damage was found, the ship returned to Naval Station Norfolk under its own power.
The failed components are under warranty and will be repaired by Northrop and the engine manufacturer, Josey said.
Engineers are now working to determine whether the problems on the New York could also affect other ships in the San Antonio class, which are built at Northrop's Gulf Coast shipyards.
The Navy is also working with the manufacturers to determine the cause of the engine problems, including an examination of maintenance practices, engine manufacturer quality control, shipbuilder practices and training, Josey said.
Northrop spokeswoman Margaret Mitchell-Jones said Friday in a statement that the company "is supporting the Navy in their analysis of the situation, however we defer any additional comment on commissioned ships to the Navy."
Homeported at Naval Station Norfolk, the ship was built in part with 7.5 tons of steel salvaged from the World Trade Center. The ship's Nov. 7 commissioning in New York City was the subject of much celebration and media attention.
Sun Jan 10, 2010 9:57 pm
This doesn't sound very good to me. The care and feeding of such important components during the long building process--several years---is the responsibility of the builder. Here's another opportunity for the taxpayor to pay through the nose.