Help me with "Battery Math"

Catt Bill/Gonzo I use 4/0 marine grade wire and lugs. I don't care about distance I want the least amount of resistance possible at the distribution point.
Bill
 
I'm w/ BillyIII on this one.

All cables have loss ( at all currents ) Use the biggest cable you can afford ( both $$$ and weight ).

If you go checking the "loss tables" out here for the recommended wire gauge they offer two columns: 10% loss and 3% loss. The difference between the two is usually one wire gauge size. I always try to upsize one size larger than the 3% size.

Many of the reasons are difficult to quantify, but include stuff like reducing voltage drop-outs when a high current device produces a sudden load. This can do things such as cause devices to reboot or shut down. In other cases it can cause long term damage due to "running hot". Whatever you can do to keep they voltage at the top of the range is a very good thing to do.

Also consider that even the recommended wire size allows a 10% loss! You fight so hard to carry those few watts, you really do not want to lose 10% ( or more, actually... ). A robust wiring system is one of the best long term things you can do to increase the total capacity of your 12V electrical system. Imho.
 
I was actually thinking 2 or 1 ga., but we'll see when the time comes. As for length, I can only speculate because the wire runs disappear behind bulkheads and fuel cells and run below the sole of the salon but aren't visible in the engine bay. If I had to guess, I'd say that about 12 to 15 feet (one way) from battery bank(s) to DC panel's 1-2-BOTH switch. I'm thinking that this is the PRIMARY source of my starting problems and will work on changing it when I get back to our home marina next week.
 
Gonzo if starting is also in the equation (I can use either of 2 house banks for starting in addition to my starting batteries) then at a minimum I wouldn't go less than #2/0 definately not #2 or #1 in your situation. Honestly #4/0 with emergency starting or primary starting at those distances. Consider a high current ACR with a remote switch for both charging, isolating from the start battery and combining for emergency starting. I use the highest current BlueSea ACR's and thier remotes at the helm.
Bill
 
Some of the problems with battery math are that they are not like a fuel tank with known numbers. Battery are rarely fully charged and each time the are discharged the size of full charge, or any charge measured by voltage, gets a bit smaller. The loads aren’t fixed either, many are variable and time or temperature dependent. Next the state of charge is difficult to measure because only after the battery sits unloaded for hours does any measurement come close to being accurate at least for wet cells. Personally I don’t believe in spending a lot of money on exotic batteries; buy deep cycle and add a bit more capacity then toss them every three years and life will be good and cheap.
That being said do your best battery math, allow for more load and poorer performance than specified as they batts age and go for it. Soon enough you will learn what 11.75 volts really means on your set up in terms of remaining charge. Oh yes another thought if you really want best efficiency use big wires clean terminals a true sine wave inverter
and learn to use a hydrometer and voltmeter, both cheap.
 
quote:

Originally posted by Billylll

Catt Bill/Gonzo I use 4/0 marine grade wire and lugs. I don't care about distance I want the least amount of resistance possible at the distribution point.
Bill






Yes, but the is a point of little or no return. So I don't really see the need to go more than say one or two sizes up from what is recommended for X length run. Good cable is not cheap after all.
 
Re the "reserve capacity"... Golf Cart batteries are rated at 75 amps, not 25 amps like automotive and many marine batteries. Using 75 amps the numbers will make a little more sense.

A Trojan T-105 has 115 reserve minutes (at 75 amps) and 225 amp hrs (20 hr rate) http://www.trojanbattery.com/Products/T-1056V.aspx

Batteries makes vary, but using the same math your Everstart with 105 reserve minutes would have about 205 amp hrs (20 hr rate).
 
The 75 amp rating makes more sense. Every thing else being the same, and using a Peukert exponential of 1.3, the battery has a rating of about 230 AH (20 hours). Luck, Dale
 
I have a number of digital voltmeters, none of cost less more than $5 at places like harbor freight. They work fine. There is no reason to pay more unless you need to measure frequency or do clamp on current readings. Those things are nice but i have never found them to be worth the extra cost and I have done lots of work. Buy cheap meters and keep one on the boat another at home etc. They really do work fine.
 
Ditto the cheap meters... WHEN (not if) you drop one in the bilge it doesn't hurt much!
 
What should be the voltage reading of a fully charged 12V battery?
 
about 12.8 volts but only after the charger and all loads have been off for 6 hours and temperature is about 75F. You can see from the forging that measureing charge isnt simple. In the real world when I hit my simple dashboard ananlog voltmeters to check the batts if they are in the range of 12.5V I figure all is well
 
about 12.8 volts but only after the charger and all loads have been off for 6 hours and temperature is about 75F. You can see from the forgoing that measuring charge isnt simple. In the real world when I hit my simple dashboard analog voltmeters to check the batts if they are in the range of 12.5V I figure all is well
 
quote:

Originally posted by Capt. Bill1

quote:

Originally posted by Billylll

Catt Bill/Gonzo I use 4/0 marine grade wire and lugs. I don't care about distance I want the least amount of resistance possible at the distribution point.
Bill






Yes, but the is a point of little or no return. So I don't really see the need to go more than say one or two sizes up from what is recommended for X length run. Good cable is not cheap after all.







Bill for my distributed power cabling I use the 3% number and go one or two sizes up on the wire. For my battery interconnections and the connection to the studs at the DC distribution panels it's 4/0. I'm trying to clarify. All starting and charging wires from the ER or Thruster are 4/0.
Bill
 
Here's how I keep my batteries healthy: I check them periodically with a digital meter; if one shows less than 12.6 volts, I initiate a slow charge and re=check c. once an hour; when the voltage shows c. 13v or near, I disconnect.
 